New Phase Begins This Last Week of August

The project marks another milestone: pile cap installation starts this week!

New spans taking shape in the water/© Janie Rosman 2014

New spans taking shape in the water/© Janie Rosman 2014

Last summer impact pile driving started, and now the main span’s steel pilings are about to be covered with 14-foot thick main span platforms. Here’s how.

Tappan Zee Constructors, LLC (TZC) President Darrell Waters said construction crews hope to set their first piece of steel on the new bridge by the end of the year.

“Between now and then, you’ll see the foundations rising, you’ll see columns coming up to meet these big pier caps we have, we’ll set those, and right after that, we put the bridge spans on it,” he said.

I’ve been watching the animation video to follow along with what I saw during the media boat tours. And it gives me goose bumps every time.

Take note of this week’s lane closures on I-87/I-287:

Monday, August 25, to Wednesday, August 27 — the northbound right lane near Exit 9 will be closed from 10 a.m. to 3 p.m., and the northbound right lane approaching the Tappan Zee Bridge will be closed from 8 p.m. to 5 a.m. Additional construction details are here.

I’d like to know what you think.

Copyright © Janie Rosman and Kaleidoscope Eyes 2014

No comments yet

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: