I Lift NY Makes First Girder Placement

Very exciting day as the first steel girder assembly was hoisted and placed onto the New NY Bridge during a seven-hour process.

lifting girder off barge

The 1,110-ton, 400-foot girder assembly – three beams assembled at the Port of Coeymans – was hoisted onto the new bridge’s 14-foot-thick foundation.

barge removed2

Dave Capobianco, a New NY Bridge project manager, said the communications conduits and wiring are not on this initial steel girder and will be on the next two-girder segment still being worked on at the port.

starting to position the girder

During the summer, barges continue loading girders from the port, unloading them at the project site and either coming to or going from both locations.

preparing the pier

I remember the 2012 and 2013 meetings that talked about shifting traffic from the current bridge to the new northern span in late 2016 or early 2017.

I’d like to know what you think.

Copyright © Janie Rosman and Kaleidoscope Eyes 2015

No comments yet

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: