Work Done, Super Crane departed Project Site

I Lift NY arriving at its destination/© Janie Rosman 2014

It arrived with great fanfare five years ago and left quietly last weekend. Its work on the project completed, the I Lift NY headed downriver accompanied by three tugboats. The photo below is from a video captured by Felice Ehrlich.

Some stats:

Its lifting Capacity is 1,929 tons, and its boom length is 328 feet. It raised 140 steel girder assemblies, four main span crossbeams, and 120 road deck panels.

First lift was April 2015
Placed first girder in June 2015
Removed first section of TZB in Nov. 2017
Final lift was May 2019

Click here for super crane history and trivia and here for more project details. Curious as to why it had three tugboat escorts.

I’d like to know what you think.

Copyright © Janie Rosman and Kaleidoscope Eyes 2019

No comments yet

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: