Archive for the ‘I Lift NY’ Tag

Super Crane Limbos Again — under Three Spans

There’s something a little different about this photo . . . /EarthCam® construction camera

Have you figured out what’s different about this photo? C’mon, you must have guessed. Here’s another hint from 14 hours earlier in the day.

Now you see it, now you don’t: super crane has moved!/EarthCam® construction camera

The project team kept silent about a certain three-span maneuver (focusing our attention on other doings); your intrepid reporter received a tip.

Back on the southern side 31 months after arriving here/EarthCam® construction camera

No crane in sight, and then it appeared on the other side of the Tappan Zee. Thank you to the source who alerted me yesterday afternoon.

Crane clears the Tappan Zee Bridge/© Janie Rosman 2014

It must have been tricky since the two new spans are considerably higher than the current bridge. You remember the planning involved last time, right? It limboed under the bridge — aided by extra low tide that added an extra foot or two of clearance — two days after its arrival.

With that in mind, the unspoken question on many people’s minds is, “When?”

If the original plans had been followed, then the westbound span would have opened in late 2016: west/northbound traffic was to have moved to the new span in December, and two months later, in February 2017, east/southbound traffic was to have moved to that span.

Hmm.

I recall hearing the bridge builder has incentives for completing the full bridge and all its accents by March/April 2018, and there would be penalties “if the Thruway Authority isn’t handed the keys to the new bridge by that date or if it’s completed even one day later.”

Said by a source working on the project. Were these guidelines abandoned?

I’d like to know what you think.

Copyright © Janie Rosman and Kaleidoscope Eyes 2017

Spring has Sprung: Nyack Buzzing with Activity

It was perfect weather to be outside Sunday, and Memorial Park in Nyack was packed with cars. We sat for a while under a tree — as luck would have it, there was a spot waiting for us — and took in the view.

This after checking out the Nyack Street Fair, always a fun experience.

That day marked five weeks since I was walking down steps and missed the step, falling and injuring my left knee and upper leg. Walking has become easier with cortisone shots, and I’ll be starting physical therapy next week. It was gorgeous outside, and I didn’t want to miss the day.

Birds flying everywhere, crowded viewing area, people enjoying the weather and checking out the bridge and the Spotter’s Guide and happy winter finally left. The giant crane was positioned near the Rockland shoreline, and people were taking pictures with their cell phones.

So when will the westbound span open? The summer before the project began, then state DOT Project Director Michael Anderson said traffic will switch to the new bridge sometime during the fourth year (2017).

Then we heard west/northbound traffic would move to the new span in December 2016, and two months later (February 2017) to move east/southbound traffic as well. Former Executive Director Robert L. Megna decided in early November to postpone the first opening until spring 2017.

Project officials are talking about “sometime this year.” I wonder if there are still built-in contract incentives for finishing the project before spring 2018 or penalties for completing it later? Is the bridge builder still on a 62-month schedule?

I’d like to know what you think.

Copyright © Janie Rosman and Kaleidoscope Eyes 2017

Educational Outreach explains the Pulley System

This cool interactive demonstration at Stemtastics in Larchmont showed kids and parents how pulleys work to lift weights like structural steel on bridges.

The I Lift NY super crane’s versabar (system) can lift up to 1700 metric tons (1928 US tons), much-needed strength when lifting pieces of structural steel.

* * * * *

It’s getting closer to when two-way traffic will shift to the the westbound span; however, I’m wondering how the belvederes will be constructed while cars are on that span. Will one lane be closed so crews can safely work on the shared use path? Will the belvederes be completed before traffic moves to the westbound span?

Here’s a view of the westbound span, where workers lower formwork over rebar. Getting there! Photos courtesy of New York State Thruway Authority.

I’d like to know what you think.

Copyright © Janie Rosman and Kaleidoscope Eyes 2017

Connecting Rockland Approach, a fifth Gantry and ongoing Main Span Channel Closures

Sleepy Hollow Lighthouse seen from the new bridge’s westbound span/© Janie Rosman 2016

Sleepy Hollow Lighthouse seen from the new bridge’s westbound span/© Janie Rosman 2016

Since media were invited onto the new westbound span, crews connected the Westchester approach and the main span, the Rockland approach and the main span are being connected, and there will soon be a fifth overhead gantry. Did we miss the fourth?

channel-closures

Tha main span navigation channel continues to be closed periodically until next December. While boaters may be pleased to hear this, I’d like to enjoy the spring, summer and fall before winter comes around again.

Click here for complete information.

I’d like to know what you think.

Copyright © Janie Rosman and Kaleidoscope Eyes 2017

Few More Glimpses around the NNYB Project Site

crane-completes-first-lift-of-2017-early-february

Did you see the I Lift NY making its 2017 debut lift on the Westchester side?

cold-weather

Crew member well-protected against the elements: BRR, it’s COLD out there!

pile-cap-for-eastbound-span-is-prepared-under-tzb

A pile cap for the as-yet-unfinished eastbound span prepared under the TZB.

structural-steel-connection

Not seen from the road: crews adjusting a section of steel for the main span.

Photos courtesy of New York State Thruway Authority.

I’d like to know what you think.

Copyright © Janie Rosman and Kaleidoscope Eyes 2017

%d bloggers like this: