Despite the delay in opening the first span, Thruway Authority Executive Director Robert Megna told its Board Monday that the new bridge will open in 2018 for less than $4 billion ($3.98 billion to be exact).
Progress to date:
- 55 percent of concrete piers are completed
- 46 percent of steel girders have been fabricated
- 34 percent of the deck panels have been fabricated
- 27 percent of girder assemblies placed
- 13 percent of the main towers poured
Other 2015 construction milestones include:
- The I Lift NY super crane’s first lift (April 2015)
- Phase 1 pile driving completed (June 2015)
- First steel girder placed (June 2015)
- Main span towers begin (August 2015)
- All planned dredging completed (September 2015)
- First concrete deck panels placed (October 2015)
To the two milestones — steel girder assemblies reach the one-mile point from the Rockland shoreline, and first concrete road deck panel placements — I’ll add another: first girder assembly placement for the westbound span (the one we’ll drive on first).